Cornwall NHS trust adds rooftop solar at four more sites in 2030 net zero push

Cornwall Partnership NHS Foundation Trust has completed DC-optimised solar PV systems at four hospital and administrative sites, forecast to generate about 206MWh a year, as it works towards a 2030 net zero target.

Aerial view of Camborne Redruth Community Hospital in Cornwall, showing rows of solar panels on the roofs of a long single-storey building next to the main hospital buildings and car parks.
Photo: Cornwall Partnership NHS Foundation Trust

Cornwall Partnership NHS Foundation Trust has completed rooftop solar PV systems at four more hospital and administrative sites in Cornwall, which are forecast to generate about 206MWh of electricity a year, according to inverter supplier SolarEdge.

The systems were designed and installed by Your Eco using SolarEdge DC-optimised inverter technology, SolarEdge said in a release issued on 24 November 2026. Together they are expected to cut the Trust's carbon emissions by around 40 tonnes a year and reduce its electricity bill by tens of thousands of pounds.

The largest of the four is a 331-panel array at Camborne Redruth Community Hospital, which serves a minor injuries unit, inpatient wards and a stroke rehabilitation unit. SolarEdge said the system is forecast to save the Trust more than £30,000 a year.

Alan Bean, Sustainability Programme Manager for Cornwall Partnership NHS Foundation Trust, said: "We're proud to continue expanding our solar programme as part of our commitment to building a more sustainable and resilient healthcare system."

The four sites

A 51-panel installation at a site supporting children with learning disabilities and autism is expected to offset about 64% of that site's energy use, the release said.

Two smaller systems have been fitted in Liskeard. A 16-panel array at The Coach House mental health resource centre is reported to generate 105% of the building's energy needs, which SolarEdge described as net-positive. The fourth system is at the Layland Short Break Home, which cares for children with complex healthcare needs; the release did not give a panel count for it.

Site Panels
Camborne Redruth Community Hospital 331
Learning disabilities and autism site 51
The Coach House, Liskeard 16

Your Eco also delivered the Trust's earlier systems at St Austell Community Hospital and the Sowenna Child and Adolescent Mental Health Unit. According to SolarEdge's own case study, the St Austell system comprises 199 solar modules controlled by an 82.8kW three-phase inverter and was forecast to produce 81,000kWh a year.

Bar chart: Panels installed at each named site (panels). Camborne Redruth Hospital: 331; Learning disabilities site: 51; The Coach House, Liskeard: 16.
Chart: Retrofit Today. Source: SolarEdge

The technology

In a SolarEdge system, power optimisers are fitted beneath each pair of panels so they operate independently of others on the same string, meaning shading or soiling on some panels does not cut the output of the rest, the company said.

SolarEdge said its S-Series optimisers include SafeDC, which is designed to lower voltage to touch-safe levels at panel level so maintenance teams and emergency responders can access the roof, and Sense Connect, which monitors for abnormal heat build-up and stops power flow before an arc can occur.

The wider programme

The Trust is also running a larger grant-funded solar programme. The Trust has said that a national funding grant of more than £2m would pay for 2,725 solar panels at 11 sites in Cornwall, with one site also receiving a battery storage system. Camborne Redruth Community Hospital was among the 11 sites listed. The Trust said it had also received funding from the NHS Energy Efficiency Fund (NEEF).

SolarEdge's release attributes the £2.2m grant to the Great British Energy scheme.

Of the grant-funded programme, Bean said: "Overall, we will reduce the electricity we buy from the grid by about 30%." He added that the electricity generated would be roughly equal to that used by 518 homes.

The Trust's green plan targets a net zero carbon footprint by 2030 and net zero carbon footprint plus by 2045, and lists installing additional solar PV systems among its carbon reduction projects. The Trust says it chose 2030 because time is of the essence; SolarEdge noted this is ten years ahead of the national NHS goal.

Nationally, the government said in October 2025 that total funding for the Great British Energy solar scheme had risen to up to £255m, with 34 NHS trusts sharing up to £30m under its expansion and around 260 NHS sites expected to benefit in total.

Following the £2.2m grant award, the Trust has committed to installing solar systems across a number of further sites it occupies, SolarEdge said.

Sources

  1. SolarEdge (release issued via Incus Media on behalf of SolarEdge, concerning Cornwall Partnership NHS Foundation Trust and Your Eco) (opens in a new tab) (accessed 2026-11-24)
  2. SolarEdge (opens in a new tab) (accessed 2026-11-24)
  3. Cornwall Partnership NHS Foundation Trust (opens in a new tab) (accessed 2026-11-24)
  4. Cornwall Partnership NHS Foundation Trust (opens in a new tab) (accessed 2026-11-24)
  5. GOV.UK (Department for Energy Security and Net Zero / Great British Energy) (opens in a new tab) (accessed 2026-11-24)

This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.

Get stories like this every Friday

The Retrofit Today weekly: the week's retrofit and net zero construction news in one email, free, and the TC Media Group monthly edition. Unsubscribe in one click.

By subscribing you agree to receive the Retrofit Today weekly and the TC Media Group monthly edition. We confirm your address first. Privacy.

More from Retrofit Today